ASHRAE 90.1-2007 Section: 9.5 - Building Area Method |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Toolbox |
Requirements: Building Area Method of Calculating Interior Lighting Power Allowance. Use the following steps to determine the interior lighting power allowance by the building area method:
Shell Buildings: If a permit applicant wishes to install some lighting in a shell building before the building's use is known, the lowest lighting power density should be used. Garages and Parking Areas: a covered garage is treated as an interior space while open parking lots and roof top parking are treated as exterior. Speculative Buildings: tenant
improvements in a core-and-shell buildings are considered new
construction and are subject to the version of 90.1 in place at the
time. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||